Total Tool Changing Time Solution

STEP 0: Pre-Calculation Summary
Formula Used
Total Tool Changing Time = Number of Tools Used*Time to Change One Tool
ttc = Nt*tc
This formula uses 3 Variables
Variables Used
Total Tool Changing Time - (Measured in Second) - Total Tool Changing Time is the cumulative time spent changing tools throughout the machining process.
Number of Tools Used - The Number of Tools Used is the total number of tools used for manufacturing a batch of products.
Time to Change One Tool - (Measured in Second) - Time to change one tool often referred to as tool change time, includes the duration taken to remove the used tool and install a new one.
STEP 1: Convert Input(s) to Base Unit
Number of Tools Used: 3 --> No Conversion Required
Time to Change One Tool: 30 Second --> 30 Second No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
ttc = Nt*tc --> 3*30
Evaluating ... ...
ttc = 90
STEP 3: Convert Result to Output's Unit
90 Second --> No Conversion Required
FINAL ANSWER
90 Second <-- Total Tool Changing Time
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Kumar Siddhant
Indian Institute of Information Technology, Design and Manufacturing (IIITDM), Jabalpur
Kumar Siddhant has created this Calculator and 400+ more calculators!
Verifier Image
Verified by Parul Keshav
National Institute of Technology (NIT), Srinagar
Parul Keshav has verified this Calculator and 400+ more calculators!

Total Production Cost Calculators

Non-Productive Cost of Each Component given Total Production Cost
​ LaTeX ​ Go Non Productive Cost of Each Component = Total Production Cost-(Batch Size*Cost of a Tool*Machining Time+Number of Tools Used*((Cost of a Tool*Time to Change One Tool)+Cost of a Tool))
Total Production Cost
​ LaTeX ​ Go Total Production Cost = Batch Size*(Cost of a Tool*(Setup Time+Machining Time))+Number of Tools Used*(Cost of a Tool*Time to Change One Tool+Cost of a Tool)
Total Non-Productive Cost given Total Production Cost
​ LaTeX ​ Go Total Non Productive Cost = Total Production Cost-(Total Machining And Operating Cost+Total Tool Changing Cost+Total Cost of Tools Used)
Total Production Cost for given Batch Size
​ LaTeX ​ Go Total Production Cost = Batch Size*Production Cost of Each Component

Total Tool Changing Time Formula

​LaTeX ​Go
Total Tool Changing Time = Number of Tools Used*Time to Change One Tool
ttc = Nt*tc

Tool Changing Time and its effect on Production.

Every time a tool has certain life within which it can perform satisfactorily, and thus replacement or re-sharpening is required to perform once tool life exceeds. Cutting or machining action is also required to pause for a certain time. An increase in cutting speed or feed rate will reduce tool life and thus frequent tool changing will be desired. This unplanned and frequent interruption in machining will impose loss to the industry.

How to Calculate Total Tool Changing Time?

Total Tool Changing Time calculator uses Total Tool Changing Time = Number of Tools Used*Time to Change One Tool to calculate the Total Tool Changing Time, The Total Tool Changing Time is defined as the total time taken by the operator or automation system to change the Tool during the production of a complete batch of components. Total Tool Changing Time is denoted by ttc symbol.

How to calculate Total Tool Changing Time using this online calculator? To use this online calculator for Total Tool Changing Time, enter Number of Tools Used (Nt) & Time to Change One Tool (tc) and hit the calculate button. Here is how the Total Tool Changing Time calculation can be explained with given input values -> 0.025 = 3*30.

FAQ

What is Total Tool Changing Time?
The Total Tool Changing Time is defined as the total time taken by the operator or automation system to change the Tool during the production of a complete batch of components and is represented as ttc = Nt*tc or Total Tool Changing Time = Number of Tools Used*Time to Change One Tool. The Number of Tools Used is the total number of tools used for manufacturing a batch of products & Time to change one tool often referred to as tool change time, includes the duration taken to remove the used tool and install a new one.
How to calculate Total Tool Changing Time?
The Total Tool Changing Time is defined as the total time taken by the operator or automation system to change the Tool during the production of a complete batch of components is calculated using Total Tool Changing Time = Number of Tools Used*Time to Change One Tool. To calculate Total Tool Changing Time, you need Number of Tools Used (Nt) & Time to Change One Tool (tc). With our tool, you need to enter the respective value for Number of Tools Used & Time to Change One Tool and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.