How to Calculate Total Production Time?
Total Production Time calculator uses Total Production Time = (Total Machining Time+Non Productive Time+Total Tool Changing Time) to calculate the Total Production Time, The Total Production Time is defined as the total time it takes to produce a complete batch of components from scratch. Total Production Time is denoted by TPT symbol.
How to calculate Total Production Time using this online calculator? To use this online calculator for Total Production Time, enter Total Machining Time (TMT), Non Productive Time (NPT) & Total Tool Changing Time (TCT) and hit the calculate button. Here is how the Total Production Time calculation can be explained with given input values -> 470 = (92+108+900).