Total Float in CPM Solution

STEP 0: Pre-Calculation Summary
Formula Used
Total Float = Latest Finish Time-Earliest Finish Time
TF0 = LFT-EFT
This formula uses 3 Variables
Variables Used
Total Float - (Measured in Day) - Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date.
Latest Finish Time - (Measured in Day) - Latest Finish Time is the latest time at which the activity can be completed without delaying the project.
Earliest Finish Time - (Measured in Day) - Earliest Finish Time is the time of an activity that occurs if the activity starts at the earliest start time and takes an estimated time t to complete the activity.
STEP 1: Convert Input(s) to Base Unit
Latest Finish Time: 50 Day --> 50 Day No Conversion Required
Earliest Finish Time: 26 Day --> 26 Day No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
TF0 = LFT-EFT --> 50-26
Evaluating ... ...
TF0 = 24
STEP 3: Convert Result to Output's Unit
2073600 Second -->24 Day (Check conversion ​here)
FINAL ANSWER
24 Day <-- Total Float
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Chandana P Dev
NSS College of Engineering (NSSCE), Palakkad
Chandana P Dev has created this Calculator and 500+ more calculators!
Verifier Image
Verified by Mithila Muthamma PA
Coorg Institute of Technology (CIT), Coorg
Mithila Muthamma PA has verified this Calculator and 700+ more calculators!

Critical Path Method Calculators

Total Float in CPM
​ LaTeX ​ Go Total Float = Latest Finish Time-Earliest Finish Time
Independent Float used in CPM
​ LaTeX ​ Go Independent Float = Free Float-Slack of an Event
Free Float used in CPM
​ LaTeX ​ Go Free Float = Total Float-Slack of an Event
Interfering Float
​ LaTeX ​ Go Interfering Float = Total Float-Free Float

Total Float in CPM Formula

​LaTeX ​Go
Total Float = Latest Finish Time-Earliest Finish Time
TF0 = LFT-EFT

What is Float?

Float, sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

What is Slack?

The Slack time for an activity is the time between its earliest and latest start time or between its earliest and latest finish time. Slack is the amount of time that an activity can be delayed past its earliest start or earliest finish without delaying the project.

How to Calculate Total Float in CPM?

Total Float in CPM calculator uses Total Float = Latest Finish Time-Earliest Finish Time to calculate the Total Float, The Total Float in CPM formula is defined as the time span by which the starting or finishing time can be delayed without delaying or affecting the overall project. The formula above is also valid as TF=LST-EST. Total Float is denoted by TF0 symbol.

How to calculate Total Float in CPM using this online calculator? To use this online calculator for Total Float in CPM, enter Latest Finish Time (LFT) & Earliest Finish Time (EFT) and hit the calculate button. Here is how the Total Float in CPM calculation can be explained with given input values -> 0.000278 = 4320000-2246400.

FAQ

What is Total Float in CPM?
The Total Float in CPM formula is defined as the time span by which the starting or finishing time can be delayed without delaying or affecting the overall project. The formula above is also valid as TF=LST-EST and is represented as TF0 = LFT-EFT or Total Float = Latest Finish Time-Earliest Finish Time. Latest Finish Time is the latest time at which the activity can be completed without delaying the project & Earliest Finish Time is the time of an activity that occurs if the activity starts at the earliest start time and takes an estimated time t to complete the activity.
How to calculate Total Float in CPM?
The Total Float in CPM formula is defined as the time span by which the starting or finishing time can be delayed without delaying or affecting the overall project. The formula above is also valid as TF=LST-EST is calculated using Total Float = Latest Finish Time-Earliest Finish Time. To calculate Total Float in CPM, you need Latest Finish Time (LFT) & Earliest Finish Time (EFT). With our tool, you need to enter the respective value for Latest Finish Time & Earliest Finish Time and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Total Float?
In this formula, Total Float uses Latest Finish Time & Earliest Finish Time. We can use 1 other way(s) to calculate the same, which is/are as follows -
  • Total Float = Free Float+Slack of an Event