Total Float given Free Float Solution

STEP 0: Pre-Calculation Summary
Formula Used
Total Float = Free Float+Slack of an Event
TF0 = FF0+S
This formula uses 3 Variables
Variables Used
Total Float - (Measured in Second) - Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date.
Free Float - (Measured in Second) - Free Float is the period by which an activity can shift in its timing without affecting the early start of any succeeding activity or event.
Slack of an Event - (Measured in Second) - Slack of an Event in a network is the difference between the latest event time and the earliest event time at its terminal point or node.
STEP 1: Convert Input(s) to Base Unit
Free Float: 18 Day --> 1555200 Second (Check conversion ​here)
Slack of an Event: 6 Day --> 518400 Second (Check conversion ​here)
STEP 2: Evaluate Formula
Substituting Input Values in Formula
TF0 = FF0+S --> 1555200+518400
Evaluating ... ...
TF0 = 2073600
STEP 3: Convert Result to Output's Unit
2073600 Second -->24 Day (Check conversion ​here)
FINAL ANSWER
24 Day <-- Total Float
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Rachana B V
The National Institute of Engineering (NIE), Mysuru
Rachana B V has created this Calculator and 25+ more calculators!
Verifier Image
Verified by Ayush Singh
Gautam Buddha University (GBU), Greater Noida
Ayush Singh has verified this Calculator and 100+ more calculators!

Critical Path Method Calculators

Total Float in CPM
​ LaTeX ​ Go Total Float = Latest Finish Time-Earliest Finish Time
Independent Float used in CPM
​ LaTeX ​ Go Independent Float = Free Float-Slack of an Event
Free Float used in CPM
​ LaTeX ​ Go Free Float = Total Float-Slack of an Event
Interfering Float
​ LaTeX ​ Go Interfering Float = Total Float-Free Float

Total Float given Free Float Formula

​LaTeX ​Go
Total Float = Free Float+Slack of an Event
TF0 = FF0+S

What is Free Float?

Free Float, per definition, is the amount of time that the activity can be delayed before any successors will be delayed. Early Start/Finish times are used to calculate the Free Float values.

What is Slack?

The Slack time for an activity is the time between its earliest and latest start time, or between its earliest and latest finish time. Slack is the amount of time that an activity can be delayed past its earliest start or earliest finish without delaying the project.

How to Calculate Total Float given Free Float?

Total Float given Free Float calculator uses Total Float = Free Float+Slack of an Event to calculate the Total Float, The Total Float given Free Float formula is defined as the maximum allowable delay in a project activity, while Free Float is the delay without impacting successor activities. Total Float is denoted by TF0 symbol.

How to calculate Total Float given Free Float using this online calculator? To use this online calculator for Total Float given Free Float, enter Free Float (FF0) & Slack of an Event (S) and hit the calculate button. Here is how the Total Float given Free Float calculation can be explained with given input values -> 0.000278 = 1555200+518400.

FAQ

What is Total Float given Free Float?
The Total Float given Free Float formula is defined as the maximum allowable delay in a project activity, while Free Float is the delay without impacting successor activities and is represented as TF0 = FF0+S or Total Float = Free Float+Slack of an Event. Free Float is the period by which an activity can shift in its timing without affecting the early start of any succeeding activity or event & Slack of an Event in a network is the difference between the latest event time and the earliest event time at its terminal point or node.
How to calculate Total Float given Free Float?
The Total Float given Free Float formula is defined as the maximum allowable delay in a project activity, while Free Float is the delay without impacting successor activities is calculated using Total Float = Free Float+Slack of an Event. To calculate Total Float given Free Float, you need Free Float (FF0) & Slack of an Event (S). With our tool, you need to enter the respective value for Free Float & Slack of an Event and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Total Float?
In this formula, Total Float uses Free Float & Slack of an Event. We can use 1 other way(s) to calculate the same, which is/are as follows -
  • Total Float = Latest Finish Time-Earliest Finish Time