Total Capital Investment Solution

STEP 0: Pre-Calculation Summary
Formula Used
Total Capital Investment = Fixed Capital Investment+Working Capital Investment
TCI = FCI+WCI
This formula uses 3 Variables
Variables Used
Total Capital Investment - Total Capital Investment in $ terms refers to the overall amount of money that a company invests in a particular project, venture, or business initiative.
Fixed Capital Investment - Fixed Capital Investment in $ term referred to as (CapEx), represents the funds that a company allocates for the acquisition, construction, expansion, or improvement of long-term physical assets.
Working Capital Investment - Working Capital Investment in $ term refers to the amount of capital that a business invests in its day-to-day operational activities to ensure smooth and efficient functioning.
STEP 1: Convert Input(s) to Base Unit
Fixed Capital Investment: 14000 --> No Conversion Required
Working Capital Investment: 6000 --> No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
TCI = FCI+WCI --> 14000+6000
Evaluating ... ...
TCI = 20000
STEP 3: Convert Result to Output's Unit
20000 --> No Conversion Required
FINAL ANSWER
20000 <-- Total Capital Investment
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Heet
Thadomal Shahani Engineering College (Tsec), Mumbai
Heet has created this Calculator and 200+ more calculators!
Verifier Image
Verified by Prerana Bakli
University of Hawaiʻi at Mānoa (UH Manoa), Hawaii, USA
Prerana Bakli has verified this Calculator and 1600+ more calculators!

Cost Estimation Calculators

Capital Cost of Project with Capacity Q2 using Sixth Tenth Rule
​ LaTeX ​ Go Capital Cost of Project with Capacity Q2 = Capital Cost of Project with Capacity Q1*((Capacity of Equipment 2/Capacity of Equipment 1)^(Value of Index))*(Cost Index 2/Cost Index 1)
Working Capital Investment
​ LaTeX ​ Go Working Capital Investment = Total Capital Investment-Fixed Capital Investment
Total Capital Investment
​ LaTeX ​ Go Total Capital Investment = Fixed Capital Investment+Working Capital Investment
Fixed Capital Investment
​ LaTeX ​ Go Fixed Capital Investment = Total Capital Investment-Working Capital Investment

Total Capital Investment Formula

​LaTeX ​Go
Total Capital Investment = Fixed Capital Investment+Working Capital Investment
TCI = FCI+WCI

What is Cost Estimation ?

Cost estimation is the process of estimating the total cost, typically in monetary terms, required to complete a project, construct a facility, develop a product, or provide a service. It is a critical aspect of project management, business planning, and decision-making. Cost estimation serves various purposes, including budgeting, financial planning, and assessing the feasibility of a project. Here are the key components and considerations of cost estimation

What is Plant Economics ?

Plant economics refers to the financial aspects of designing, building, operating, and managing a plant or industrial facility. It involves the analysis of the costs and revenues associated with the establishment and operation of a facility to determine its economic viability and profitability. Plant economics plays a pivotal role in decision-making processes related to investments in new plants, expansions, upgrades, or optimizing existing facilities.

How to Calculate Total Capital Investment?

Total Capital Investment calculator uses Total Capital Investment = Fixed Capital Investment+Working Capital Investment to calculate the Total Capital Investment, The Total Capital Investment is the sum of all the capital costs required to establish and operate a project, plant, or business. TCI includes both the initial capital costs (capital expenditures or CAPEX) and any additional capital costs incurred during the project's lifetime. Total Capital Investment is denoted by TCI symbol.

How to calculate Total Capital Investment using this online calculator? To use this online calculator for Total Capital Investment, enter Fixed Capital Investment (FCI) & Working Capital Investment (WCI) and hit the calculate button. Here is how the Total Capital Investment calculation can be explained with given input values -> 6100 = 14000+6000.

FAQ

What is Total Capital Investment?
The Total Capital Investment is the sum of all the capital costs required to establish and operate a project, plant, or business. TCI includes both the initial capital costs (capital expenditures or CAPEX) and any additional capital costs incurred during the project's lifetime and is represented as TCI = FCI+WCI or Total Capital Investment = Fixed Capital Investment+Working Capital Investment. Fixed Capital Investment in $ term referred to as (CapEx), represents the funds that a company allocates for the acquisition, construction, expansion, or improvement of long-term physical assets & Working Capital Investment in $ term refers to the amount of capital that a business invests in its day-to-day operational activities to ensure smooth and efficient functioning.
How to calculate Total Capital Investment?
The Total Capital Investment is the sum of all the capital costs required to establish and operate a project, plant, or business. TCI includes both the initial capital costs (capital expenditures or CAPEX) and any additional capital costs incurred during the project's lifetime is calculated using Total Capital Investment = Fixed Capital Investment+Working Capital Investment. To calculate Total Capital Investment, you need Fixed Capital Investment (FCI) & Working Capital Investment (WCI). With our tool, you need to enter the respective value for Fixed Capital Investment & Working Capital Investment and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.