Number of Passes given Compaction Production by Compaction Equipment Solution

STEP 0: Pre-Calculation Summary
Formula Used
Number of Passes = (16*Width of Roller*Roller Speed*Efficiency Factor*Lift Thickness*Pay Ratio)/Production due to Compaction
P = (16*W*S*E*L*PR)/y
This formula uses 7 Variables
Variables Used
Number of Passes - Number of Passes is the number of times a compactor (such as a vibratory roller or a plate compactor) passes over a specific area of soil or aggregate during compaction.
Width of Roller - (Measured in Meter) - Width of Roller is the physical width of the roller used in compaction processes, such as those employed in soil and pavement construction.
Roller Speed - (Measured in Meter per Second) - Roller Speed is the velocity at which a compaction roller moves over soil or other materials during the compaction process.
Efficiency Factor - The Efficiency Factor is a dimensionless parameter used to relate the strength or stiffness of improved soil (after treatment) to its original, untreated state.
Lift Thickness - (Measured in Meter) - Lift Thickness is the depth of a compacted layer of fill material placed during construction. This term is important in the compaction process, where fill material is often placed in layers.
Pay Ratio - (Measured in Cubic Meter) - Pay Ratio is the ratio between the effective stress and the total stress in soil mechanics.
Production due to Compaction - (Measured in Cubic Meter per Second) - Production due to Compaction is the exertion of force on something so that it becomes denser.
STEP 1: Convert Input(s) to Base Unit
Width of Roller: 2.89 Meter --> 2.89 Meter No Conversion Required
Roller Speed: 3 Kilometer per Hour --> 0.833333333333333 Meter per Second (Check conversion ​here)
Efficiency Factor: 0.5 --> No Conversion Required
Lift Thickness: 7.175 Millimeter --> 0.007175 Meter (Check conversion ​here)
Pay Ratio: 2.99 Cubic Meter --> 2.99 Cubic Meter No Conversion Required
Production due to Compaction: 297.59 Cubic Meter per Hour --> 0.0826638888888889 Cubic Meter per Second (Check conversion ​here)
STEP 2: Evaluate Formula
Substituting Input Values in Formula
P = (16*W*S*E*L*PR)/y --> (16*2.89*0.833333333333333*0.5*0.007175*2.99)/0.0826638888888889
Evaluating ... ...
P = 5.00015934675224
STEP 3: Convert Result to Output's Unit
5.00015934675224 --> No Conversion Required
FINAL ANSWER
5.00015934675224 5.000159 <-- Number of Passes
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Suraj Kumar
Birsa Institute of Technology (BIT), Sindri
Suraj Kumar has created this Calculator and 2100+ more calculators!
Verifier Image
Verified by Ishita Goyal
Meerut Institute of Engineering and Technology (MIET), Meerut
Ishita Goyal has verified this Calculator and 2600+ more calculators!

Compaction Equipment Calculators

Thickness of Lift given Compaction Production by Compaction Equipment
​ Go Lift Thickness = (Production due to Compaction*Number of Passes)/(16*Width of Roller*Roller Speed*Efficiency Factor*Pay Ratio)
Width of Roller given Compaction Production by Compaction Equipment
​ Go Width of Roller = (Production due to Compaction*Number of Passes)/(16*Roller Speed*Lift Thickness*Pay Ratio*Efficiency Factor)
Speed of Roller given Compaction Production by Compaction Equipment
​ Go Roller Speed = (Production due to Compaction*Number of Passes)/(16*Width of Roller*Lift Thickness*Pay Ratio*Efficiency Factor)
Compaction Production by Compaction Equipment
​ Go Production due to Compaction = (16*Width of Roller*Roller Speed*Lift Thickness*Efficiency Factor*Pay Ratio)/Number of Passes

Number of Passes given Compaction Production by Compaction Equipment Formula

Number of Passes = (16*Width of Roller*Roller Speed*Efficiency Factor*Lift Thickness*Pay Ratio)/Production due to Compaction
P = (16*W*S*E*L*PR)/y

What is Compaction?

In geotechnical engineering, soil compaction is the process in which stress is applied to a soil causes densification as air is displaced from the pores between the soil grains.

How to Calculate Number of Passes given Compaction Production by Compaction Equipment?

Number of Passes given Compaction Production by Compaction Equipment calculator uses Number of Passes = (16*Width of Roller*Roller Speed*Efficiency Factor*Lift Thickness*Pay Ratio)/Production due to Compaction to calculate the Number of Passes, The Number of Passes given Compaction Production by Compaction Equipment formula is defined as the number of times a compaction machine, such as a roller, passes over a particular area of soil or aggregate. Each pass contributes to the densification of the material by applying mechanical force, reducing air voids, and increasing particle interlock. Number of Passes is denoted by P symbol.

How to calculate Number of Passes given Compaction Production by Compaction Equipment using this online calculator? To use this online calculator for Number of Passes given Compaction Production by Compaction Equipment, enter Width of Roller (W), Roller Speed (S), Efficiency Factor (E), Lift Thickness (L), Pay Ratio (PR) & Production due to Compaction (y) and hit the calculate button. Here is how the Number of Passes given Compaction Production by Compaction Equipment calculation can be explained with given input values -> 5.32207 = (16*2.89*0.833333333333333*0.5*0.007175*2.99)/0.0826638888888889.

FAQ

What is Number of Passes given Compaction Production by Compaction Equipment?
The Number of Passes given Compaction Production by Compaction Equipment formula is defined as the number of times a compaction machine, such as a roller, passes over a particular area of soil or aggregate. Each pass contributes to the densification of the material by applying mechanical force, reducing air voids, and increasing particle interlock and is represented as P = (16*W*S*E*L*PR)/y or Number of Passes = (16*Width of Roller*Roller Speed*Efficiency Factor*Lift Thickness*Pay Ratio)/Production due to Compaction. Width of Roller is the physical width of the roller used in compaction processes, such as those employed in soil and pavement construction, Roller Speed is the velocity at which a compaction roller moves over soil or other materials during the compaction process, The Efficiency Factor is a dimensionless parameter used to relate the strength or stiffness of improved soil (after treatment) to its original, untreated state, Lift Thickness is the depth of a compacted layer of fill material placed during construction. This term is important in the compaction process, where fill material is often placed in layers, Pay Ratio is the ratio between the effective stress and the total stress in soil mechanics & Production due to Compaction is the exertion of force on something so that it becomes denser.
How to calculate Number of Passes given Compaction Production by Compaction Equipment?
The Number of Passes given Compaction Production by Compaction Equipment formula is defined as the number of times a compaction machine, such as a roller, passes over a particular area of soil or aggregate. Each pass contributes to the densification of the material by applying mechanical force, reducing air voids, and increasing particle interlock is calculated using Number of Passes = (16*Width of Roller*Roller Speed*Efficiency Factor*Lift Thickness*Pay Ratio)/Production due to Compaction. To calculate Number of Passes given Compaction Production by Compaction Equipment, you need Width of Roller (W), Roller Speed (S), Efficiency Factor (E), Lift Thickness (L), Pay Ratio (PR) & Production due to Compaction (y). With our tool, you need to enter the respective value for Width of Roller, Roller Speed, Efficiency Factor, Lift Thickness, Pay Ratio & Production due to Compaction and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
Let Others Know
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!