Most Likely Time given Expected Time Solution

STEP 0: Pre-Calculation Summary
Formula Used
Most Likely Time = (6*Mean Time-Optimistic Time-Pessimistic Time)/4
tm = (6*te-t0-tp)/4
This formula uses 4 Variables
Variables Used
Most Likely Time - (Measured in Day) - Most Likely Time is the normal time activity would take.
Mean Time - (Measured in Day) - Mean Time, also called expected time is the time needed to complete an activity.
Optimistic Time - (Measured in Day) - Optimistic Time is the shortest possible time to complete the activity if all goes well.
Pessimistic Time - (Measured in Day) - A Pessimistic Time is the longest time that an activity could take if everything is wrong.
STEP 1: Convert Input(s) to Base Unit
Mean Time: 4 Day --> 4 Day No Conversion Required
Optimistic Time: 2 Day --> 2 Day No Conversion Required
Pessimistic Time: 10 Day --> 10 Day No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
tm = (6*te-t0-tp)/4 --> (6*4-2-10)/4
Evaluating ... ...
tm = 3
STEP 3: Convert Result to Output's Unit
259200 Second -->3 Day (Check conversion ​here)
FINAL ANSWER
3 Day <-- Most Likely Time
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Chandana P Dev
NSS College of Engineering (NSSCE), Palakkad
Chandana P Dev has created this Calculator and 500+ more calculators!
Verifier Image
Verified by Mithila Muthamma PA
Coorg Institute of Technology (CIT), Coorg
Mithila Muthamma PA has verified this Calculator and 700+ more calculators!

Project Evaluation and Review Technique Calculators

Optimistic Time given Expected Time
​ LaTeX ​ Go Optimistic Time = (6*Mean Time)-(4*Most Likely Time)-Pessimistic Time
Mean or Expected Time
​ LaTeX ​ Go Mean Time = (Optimistic Time+(4*Most Likely Time)+Pessimistic Time)/6
Most Likely Time given Expected Time
​ LaTeX ​ Go Most Likely Time = (6*Mean Time-Optimistic Time-Pessimistic Time)/4
Pessimistic Time given Expected Time
​ LaTeX ​ Go Pessimistic Time = 6*Mean Time-Optimistic Time-4*Most Likely Time

Most Likely Time given Expected Time Formula

​LaTeX ​Go
Most Likely Time = (6*Mean Time-Optimistic Time-Pessimistic Time)/4
tm = (6*te-t0-tp)/4

What is PERT ?

Program Evaluation and Review Technique (PERT) is a method used to examine the tasks that are in a schedule and determine a variation of the Critical Path Method (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project. It estimates the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected.

What is Central Limit Theorem and Critical Path?

Central Limit Theorem: The theorem states that a project consists of a large number of activities, where each activity has its own mean time (te), standard deviation (σ), variance (σ2) and also its own ß-distribution curve.
Critical Path: The time-wise longest path is the critical path. In this path, any type of delay, in any event, will cause a delay in the project. These are shown by double lines or dark lines in a network.

How to Calculate Most Likely Time given Expected Time?

Most Likely Time given Expected Time calculator uses Most Likely Time = (6*Mean Time-Optimistic Time-Pessimistic Time)/4 to calculate the Most Likely Time, The Most Likely Time given Expected Time formula is defined as the time required to complete an activity under normal working conditions. Most Likely Time is denoted by tm symbol.

How to calculate Most Likely Time given Expected Time using this online calculator? To use this online calculator for Most Likely Time given Expected Time, enter Mean Time (te), Optimistic Time (t0) & Pessimistic Time (tp) and hit the calculate button. Here is how the Most Likely Time given Expected Time calculation can be explained with given input values -> 3.5E-5 = (6*345600-172800-864000)/4.

FAQ

What is Most Likely Time given Expected Time?
The Most Likely Time given Expected Time formula is defined as the time required to complete an activity under normal working conditions and is represented as tm = (6*te-t0-tp)/4 or Most Likely Time = (6*Mean Time-Optimistic Time-Pessimistic Time)/4. Mean Time, also called expected time is the time needed to complete an activity, Optimistic Time is the shortest possible time to complete the activity if all goes well & A Pessimistic Time is the longest time that an activity could take if everything is wrong.
How to calculate Most Likely Time given Expected Time?
The Most Likely Time given Expected Time formula is defined as the time required to complete an activity under normal working conditions is calculated using Most Likely Time = (6*Mean Time-Optimistic Time-Pessimistic Time)/4. To calculate Most Likely Time given Expected Time, you need Mean Time (te), Optimistic Time (t0) & Pessimistic Time (tp). With our tool, you need to enter the respective value for Mean Time, Optimistic Time & Pessimistic Time and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.