Maximum Steel Quantity Estimation for Foundations Solution

STEP 0: Pre-Calculation Summary
Formula Used
Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel
Qsteel = 0.008*Nocolumns*Vfoundation*ρsteel
This formula uses 4 Variables
Variables Used
Maximum Quantity of Steel - (Measured in Kilogram) - Maximum Quantity of Steel is the maximum mass of steel in kg that we will be requiring in the construction of a particular RCC component.
Number of Columns - Number of Columns defines the total number of RCC beams in the structure of a given specification.
Volume of Foundation - (Measured in Cubic Meter) - Volume of foundation is obtained by multiplying length of the footing X Width of the footing X Depth of the footing.
Density of Steel - (Measured in Kilogram per Cubic Meter) - Density of steel is usually taken as 7860kg/m3 in civil domain. Though there exists steel of different densities Carbon steel's density is about 7.84 g/cm3,stainless steel's is about 8.03 g/cm3.
STEP 1: Convert Input(s) to Base Unit
Number of Columns: 12 --> No Conversion Required
Volume of Foundation: 1.92 Cubic Meter --> 1.92 Cubic Meter No Conversion Required
Density of Steel: 7860 Kilogram per Cubic Meter --> 7860 Kilogram per Cubic Meter No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
Qsteel = 0.008*Nocolumns*Vfoundationsteel --> 0.008*12*1.92*7860
Evaluating ... ...
Qsteel = 1448.7552
STEP 3: Convert Result to Output's Unit
1448.7552 Kilogram --> No Conversion Required
FINAL ANSWER
1448.7552 1448.755 Kilogram <-- Maximum Quantity of Steel
(Calculation completed in 00.020 seconds)

Credits

Creator Image
Created by Smriti Singh
MIT Academy of engineering, Pune (MITAOE), Alandi, Pune
Smriti Singh has created this Calculator and 25+ more calculators!
Verifier Image
Verified by Swarnima Singh
NIT Jaipur (mnitj), jaipur
Swarnima Singh has verified this Calculator and 10 more calculators!

Quantity of Steel Estimation Calculators

Maximum Steel Quantity Estimation for Foundations
​ LaTeX ​ Go Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel
Maximum Steel Quantity Estimation for Columns
​ LaTeX ​ Go Maximum Quantity of Steel = 0.06*Number of Columns*Volume of Columns*Density of Steel
Maximum Steel Quantity Estimation for RCC Slab
​ LaTeX ​ Go Maximum Quantity of Steel = 0.015*Area of Slab*Thickness of Slab*Density of Steel
Maximum Steel Quantity Estimation for Beams
​ LaTeX ​ Go Maximum Quantity of Steel = 0.02*Number of Beams*Volume of Beam*Density of Steel

Maximum Steel Quantity Estimation for Foundations Formula

​LaTeX ​Go
Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel
Qsteel = 0.008*Nocolumns*Vfoundation*ρsteel

What is the Maximum & Minimum Quantity of Steel required for Foundations?

As per the standard the minimum percentage of steel is considered as 0.7% of the volume of the concrete required and the maximum percentage of steel is 0.8% of the volume of the concrete required for making the foundation.

Important note.

Kindly take a note that here volume of foundation defines volume of 1 single foundation.
Or we can say ,
Volume of foundation =Length of the footing X Width of the footing X Depth of the footing

How to Calculate Maximum Steel Quantity Estimation for Foundations?

Maximum Steel Quantity Estimation for Foundations calculator uses Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel to calculate the Maximum Quantity of Steel, The Maximum Steel Quantity Estimation for Foundations formula is defined as calculating the amount of steel in kgs that will be required for foundations of a given number of foundations having the same specifications in the structure. Here, the volume of the foundation =length of the footing X width of the footing X depth of the footing. Maximum Quantity of Steel is denoted by Qsteel symbol.

How to calculate Maximum Steel Quantity Estimation for Foundations using this online calculator? To use this online calculator for Maximum Steel Quantity Estimation for Foundations, enter Number of Columns (Nocolumns), Volume of Foundation (Vfoundation) & Density of Steel steel) and hit the calculate button. Here is how the Maximum Steel Quantity Estimation for Foundations calculation can be explained with given input values -> 1448.755 = 0.008*12*1.92*7860.

FAQ

What is Maximum Steel Quantity Estimation for Foundations?
The Maximum Steel Quantity Estimation for Foundations formula is defined as calculating the amount of steel in kgs that will be required for foundations of a given number of foundations having the same specifications in the structure. Here, the volume of the foundation =length of the footing X width of the footing X depth of the footing and is represented as Qsteel = 0.008*Nocolumns*Vfoundationsteel or Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel. Number of Columns defines the total number of RCC beams in the structure of a given specification, Volume of foundation is obtained by multiplying length of the footing X Width of the footing X Depth of the footing & Density of steel is usually taken as 7860kg/m3 in civil domain. Though there exists steel of different densities Carbon steel's density is about 7.84 g/cm3,stainless steel's is about 8.03 g/cm3.
How to calculate Maximum Steel Quantity Estimation for Foundations?
The Maximum Steel Quantity Estimation for Foundations formula is defined as calculating the amount of steel in kgs that will be required for foundations of a given number of foundations having the same specifications in the structure. Here, the volume of the foundation =length of the footing X width of the footing X depth of the footing is calculated using Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel. To calculate Maximum Steel Quantity Estimation for Foundations, you need Number of Columns (Nocolumns), Volume of Foundation (Vfoundation) & Density of Steel steel). With our tool, you need to enter the respective value for Number of Columns, Volume of Foundation & Density of Steel and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Maximum Quantity of Steel?
In this formula, Maximum Quantity of Steel uses Number of Columns, Volume of Foundation & Density of Steel. We can use 3 other way(s) to calculate the same, which is/are as follows -
  • Maximum Quantity of Steel = 0.02*Number of Beams*Volume of Beam*Density of Steel
  • Maximum Quantity of Steel = 0.06*Number of Columns*Volume of Columns*Density of Steel
  • Maximum Quantity of Steel = 0.015*Area of Slab*Thickness of Slab*Density of Steel
Let Others Know
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!