Independent Float Solution

STEP 0: Pre-Calculation Summary
Formula Used
Independent Float = Early Finish Time-Late Start Time-Activity Time
IF0 = EFT-LST-tactivity
This formula uses 4 Variables
Variables Used
Independent Float - (Measured in Second) - Independent Float is that portion of the total float within which an activity can be delayed to start without affecting the float of the preceding activities.
Early Finish Time - (Measured in Second) - Early Finish Time is the earliest point in time when the scheduled activity can complete.
Late Start Time - (Measured in Second) - Late Start Time is the latest point in time when the scheduled activity can begin so as not to delay the project completion date or any constraint.
Activity Time - (Measured in Second) - Activity time is the estimated task duration based on preceding logic and constraints.
STEP 1: Convert Input(s) to Base Unit
Early Finish Time: 46 Day --> 3974400 Second (Check conversion ​here)
Late Start Time: 23 Day --> 1987200 Second (Check conversion ​here)
Activity Time: 20 Day --> 1728000 Second (Check conversion ​here)
STEP 2: Evaluate Formula
Substituting Input Values in Formula
IF0 = EFT-LST-tactivity --> 3974400-1987200-1728000
Evaluating ... ...
IF0 = 259200
STEP 3: Convert Result to Output's Unit
259200 Second -->3 Day (Check conversion ​here)
FINAL ANSWER
3 Day <-- Independent Float
(Calculation completed in 00.020 seconds)

Credits

Creator Image
Created by Suman Ray Pramanik
Indian Institute of Technology (IIT), Kanpur
Suman Ray Pramanik has created this Calculator and 50+ more calculators!
Verifier Image
Verified by Akshada Kulkarni
National Institute of Information Technology (NIIT), Neemrana
Akshada Kulkarni has verified this Calculator and 900+ more calculators!

Time Estimation Calculators

Expected Waiting Time for Customers in Queue
​ LaTeX ​ Go Expected Waiting Time for Customers in Queue = Mean Arrival Rate/(Mean Service Rate*(Mean Service Rate-Mean Arrival Rate))
Free Float
​ LaTeX ​ Go Free Float = Early Finish Time-Early Start Time-Activity Time
Expected Waiting Time for Customers in System
​ LaTeX ​ Go Expected Waiting Time for Customers in System = 1/(Mean Service Rate-Mean Arrival Rate)
Early Finish Time
​ LaTeX ​ Go Early Finish Time = Early Start Time+Safety Stock

Independent Float Formula

​LaTeX ​Go
Independent Float = Early Finish Time-Late Start Time-Activity Time
IF0 = EFT-LST-tactivity

What is Independent Float?

Independent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities. Independent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities. It is computed for activity by subtracting the tail event slack from its total float.

How to Calculate Independent Float?

Independent Float calculator uses Independent Float = Early Finish Time-Late Start Time-Activity Time to calculate the Independent Float, Independent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities. Independent Float is denoted by IF0 symbol.

How to calculate Independent Float using this online calculator? To use this online calculator for Independent Float, enter Early Finish Time (EFT), Late Start Time (LST) & Activity Time (tactivity) and hit the calculate button. Here is how the Independent Float calculation can be explained with given input values -> 3.5E-5 = 3974400-1987200-1728000.

FAQ

What is Independent Float?
Independent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities and is represented as IF0 = EFT-LST-tactivity or Independent Float = Early Finish Time-Late Start Time-Activity Time. Early Finish Time is the earliest point in time when the scheduled activity can complete, Late Start Time is the latest point in time when the scheduled activity can begin so as not to delay the project completion date or any constraint & Activity time is the estimated task duration based on preceding logic and constraints.
How to calculate Independent Float?
Independent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities is calculated using Independent Float = Early Finish Time-Late Start Time-Activity Time. To calculate Independent Float, you need Early Finish Time (EFT), Late Start Time (LST) & Activity Time (tactivity). With our tool, you need to enter the respective value for Early Finish Time, Late Start Time & Activity Time and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.