Free Float given Indenpendent Float Solution

STEP 0: Pre-Calculation Summary
Formula Used
Free Float = Independent Float+Slack of an Event
FF0 = IF0+S
This formula uses 3 Variables
Variables Used
Free Float - (Measured in Second) - Free Float is the period by which an activity can shift in its timing without affecting the early start of any succeeding activity or event.
Independent Float - (Measured in Second) - Independent Float is that portion of the total float within which an activity can be delayed to start without affecting the float of the preceding activities.
Slack of an Event - (Measured in Second) - Slack of an Event in a network is the difference between the latest event time and the earliest event time at its terminal point or node.
STEP 1: Convert Input(s) to Base Unit
Independent Float: 12 Day --> 1036800 Second (Check conversion ​here)
Slack of an Event: 6 Day --> 518400 Second (Check conversion ​here)
STEP 2: Evaluate Formula
Substituting Input Values in Formula
FF0 = IF0+S --> 1036800+518400
Evaluating ... ...
FF0 = 1555200
STEP 3: Convert Result to Output's Unit
1555200 Second -->18 Day (Check conversion ​here)
FINAL ANSWER
18 Day <-- Free Float
(Calculation completed in 00.020 seconds)

Credits

Creator Image
Created by Rachana B V
The National Institute of Engineering (NIE), Mysuru
Rachana B V has created this Calculator and 25+ more calculators!
Verifier Image
Verified by Ayush Singh
Gautam Buddha University (GBU), Greater Noida
Ayush Singh has verified this Calculator and 100+ more calculators!

Critical Path Method Calculators

Total Float in CPM
​ LaTeX ​ Go Total Float = Latest Finish Time-Earliest Finish Time
Independent Float used in CPM
​ LaTeX ​ Go Independent Float = Free Float-Slack of an Event
Free Float used in CPM
​ LaTeX ​ Go Free Float = Total Float-Slack of an Event
Interfering Float
​ LaTeX ​ Go Interfering Float = Total Float-Free Float

Free Float given Indenpendent Float Formula

​LaTeX ​Go
Free Float = Independent Float+Slack of an Event
FF0 = IF0+S

What is Independent Float?

Independent Float is defined as the amount of time an activity's start time can be delayed without affecting the earliest start time of any successors. So independent float is the delay in any project tasks that have no bearing on the early finish date of the project.

What is Tail Event Slack?

The Tail Event Slack of an activity in a network is the slack at the tail (or starting point) of an activity. In other words, tail event slack of an activity in a network is the difference between the latest event time and the earliest event time at its tail (or starting point or node).

How to Calculate Free Float given Indenpendent Float?

Free Float given Indenpendent Float calculator uses Free Float = Independent Float+Slack of an Event to calculate the Free Float, The Free Float given Indenpendent Float formula is defined as the time available for an activity while considering dependencies, minus independent float, representing schedule flexibility. Free Float is denoted by FF0 symbol.

How to calculate Free Float given Indenpendent Float using this online calculator? To use this online calculator for Free Float given Indenpendent Float, enter Independent Float (IF0) & Slack of an Event (S) and hit the calculate button. Here is how the Free Float given Indenpendent Float calculation can be explained with given input values -> 0.000208 = 1036800+518400.

FAQ

What is Free Float given Indenpendent Float?
The Free Float given Indenpendent Float formula is defined as the time available for an activity while considering dependencies, minus independent float, representing schedule flexibility and is represented as FF0 = IF0+S or Free Float = Independent Float+Slack of an Event. Independent Float is that portion of the total float within which an activity can be delayed to start without affecting the float of the preceding activities & Slack of an Event in a network is the difference between the latest event time and the earliest event time at its terminal point or node.
How to calculate Free Float given Indenpendent Float?
The Free Float given Indenpendent Float formula is defined as the time available for an activity while considering dependencies, minus independent float, representing schedule flexibility is calculated using Free Float = Independent Float+Slack of an Event. To calculate Free Float given Indenpendent Float, you need Independent Float (IF0) & Slack of an Event (S). With our tool, you need to enter the respective value for Independent Float & Slack of an Event and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Free Float?
In this formula, Free Float uses Independent Float & Slack of an Event. We can use 1 other way(s) to calculate the same, which is/are as follows -
  • Free Float = Total Float-Slack of an Event
Let Others Know
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!