Falling Rate Drying Time from Initial to Final Weight of Moisture Solution

STEP 0: Pre-Calculation Summary
Formula Used
Falling Rate Drying Time = ((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Drying Surface Area*Rate of Constant Drying Period))*(ln((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Final Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)))
tf = ((Mi(Falling)-MEq)/(A*Nc))*(ln((Mi(Falling)-MEq)/(Mf(Falling)-MEq)))
This formula uses 1 Functions, 6 Variables
Functions Used
ln - The natural logarithm, also known as the logarithm to the base e, is the inverse function of the natural exponential function., ln(Number)
Variables Used
Falling Rate Drying Time - (Measured in Second) - The Falling rate drying time is the time taken for drying operation in the falling rate period.
Initial Weight of Moisture for Falling Rate Period - (Measured in Kilogram) - The Initial Weight of Moisture for Falling Rate Period is the amount of moisture in kg present in the wet solid initially for drying operation.
Equilibrium Weight of Moisture - (Measured in Kilogram) - The Equilibrium Weight of Moisture is the amount of moisture in kg present in the solid that is in equilibrium with the solid for the given drying conditions.
Drying Surface Area - (Measured in Square Meter) - The Drying Surface Area is the total area in the drying mass transfer operation i.e. exposed in contact with the drying medium.
Rate of Constant Drying Period - (Measured in Kilogram per Second per Square Meter) - The Rate of Constant Drying Period is the rate of drying that takes place for a given set of drying conditions in the constant rate period.
Final Weight of Moisture for Falling Rate Period - (Measured in Kilogram) - The Final Weight of Moisture for Falling Rate Period is the amount of moisture in kg present in the solid after the completion of drying operation.
STEP 1: Convert Input(s) to Base Unit
Initial Weight of Moisture for Falling Rate Period: 10 Kilogram --> 10 Kilogram No Conversion Required
Equilibrium Weight of Moisture: 5 Kilogram --> 5 Kilogram No Conversion Required
Drying Surface Area: 0.1 Square Meter --> 0.1 Square Meter No Conversion Required
Rate of Constant Drying Period: 2 Kilogram per Second per Square Meter --> 2 Kilogram per Second per Square Meter No Conversion Required
Final Weight of Moisture for Falling Rate Period: 6.5 Kilogram --> 6.5 Kilogram No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
tf = ((Mi(Falling)-MEq)/(A*Nc))*(ln((Mi(Falling)-MEq)/(Mf(Falling)-MEq))) --> ((10-5)/(0.1*2))*(ln((10-5)/(6.5-5)))
Evaluating ... ...
tf = 30.0993201081484
STEP 3: Convert Result to Output's Unit
30.0993201081484 Second --> No Conversion Required
FINAL ANSWER
30.0993201081484 30.09932 Second <-- Falling Rate Drying Time
(Calculation completed in 00.021 seconds)

Credits

Creator Image
Created by Vaibhav Mishra
DJ Sanghvi College of Engineering (DJSCE), Mumbai
Vaibhav Mishra has created this Calculator and 300+ more calculators!
Verifier Image
Verified by Prerana Bakli
University of Hawaiʻi at Mānoa (UH Manoa), Hawaii, USA
Prerana Bakli has verified this Calculator and 1600+ more calculators!

Drying from Initial to Final Moisture Calculators

Drying Surface Area based on Initial to Final Moisture Content for Falling Rate Period
​ LaTeX ​ Go Drying Surface Area = (Dry Weight of Solid/Falling Rate Drying Time)*((Initial Moisture Content for Falling Rate Period-Equilibrium Moisture Content)/Rate of Constant Drying Period)*(ln((Initial Moisture Content for Falling Rate Period-Equilibrium Moisture Content)/(Final Moisture Content for Falling Rate Period-Equilibrium Moisture Content)))
Falling Rate Drying Time from Initial to Final Moisture
​ LaTeX ​ Go Falling Rate Drying Time = (Dry Weight of Solid/Drying Surface Area)*((Initial Moisture Content for Falling Rate Period-Equilibrium Moisture Content)/Rate of Constant Drying Period)*(ln((Initial Moisture Content for Falling Rate Period-Equilibrium Moisture Content)/(Final Moisture Content for Falling Rate Period-Equilibrium Moisture Content)))
Drying Surface Area based on Initial to Final Weight of Moisture for Falling Rate Period
​ LaTeX ​ Go Drying Surface Area = ((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Falling Rate Drying Time*Rate of Constant Drying Period))*(ln((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Final Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)))
Falling Rate Drying Time from Initial to Final Weight of Moisture
​ LaTeX ​ Go Falling Rate Drying Time = ((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Drying Surface Area*Rate of Constant Drying Period))*(ln((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Final Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)))

Important Formulas in Drying Mass Transfer Operation Calculators

Constant Drying Time from Initial to Critical Moisture Content
​ LaTeX ​ Go Constant Rate Drying Time = Dry Weight of Solid*((Initial Moisture Content for Constant Rate Period-Critical Moisture Content))/((Drying Surface Area*Rate of Constant Drying Period))
Critical Moisture Content based on Initial Moisture Content for Constant Rate Period
​ LaTeX ​ Go Critical Moisture Content = Initial Moisture Content for Constant Rate Period-((Drying Surface Area*Constant Rate Drying Time*Rate of Constant Drying Period)/Dry Weight of Solid)
Constant Drying Time from Initial to Critical Weight of Moisture
​ LaTeX ​ Go Constant Rate Drying Time = (Initial Weight of Moisture for Constant Rate-Critical Weight of Moisture)/(Drying Surface Area*Rate of Constant Drying Period)
Total Drying Time based on Constant Drying Time and Falling Drying Time
​ LaTeX ​ Go Total Drying Time = Constant Rate Drying Time+Falling Rate Drying Time

Falling Rate Drying Time from Initial to Final Weight of Moisture Formula

​LaTeX ​Go
Falling Rate Drying Time = ((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Drying Surface Area*Rate of Constant Drying Period))*(ln((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Final Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)))
tf = ((Mi(Falling)-MEq)/(A*Nc))*(ln((Mi(Falling)-MEq)/(Mf(Falling)-MEq)))

What is Falling Rate Period Drying?

The falling rate drying period is a stage in the drying process where the rate of moisture removal from the material decreases over time as the internal moisture content of the material is reduced. During this period, the drying rate is typically controlled by the rate of moisture diffusion within the material, which is slower than the rate of heat and mass transfer at the surface of the material. In this stage, the moisture content of the material decreases more slowly than during the constant rate drying period, as the remaining moisture is located deeper within the material and must diffuse to the surface before it can be removed. The length of the falling rate period depends on the properties of the material being dried, such as its porosity, particle size, and moisture distribution.

How to Calculate Falling Rate Drying Time from Initial to Final Weight of Moisture?

Falling Rate Drying Time from Initial to Final Weight of Moisture calculator uses Falling Rate Drying Time = ((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Drying Surface Area*Rate of Constant Drying Period))*(ln((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Final Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture))) to calculate the Falling Rate Drying Time, The Falling Rate Drying Time from Initial to Final Weight of Moisture formula is defined as the time taken for drying in the falling rate period based on drying from initial to final weight of moisture for specified drying conditions. Falling Rate Drying Time is denoted by tf symbol.

How to calculate Falling Rate Drying Time from Initial to Final Weight of Moisture using this online calculator? To use this online calculator for Falling Rate Drying Time from Initial to Final Weight of Moisture, enter Initial Weight of Moisture for Falling Rate Period (Mi(Falling)), Equilibrium Weight of Moisture (MEq), Drying Surface Area (A), Rate of Constant Drying Period (Nc) & Final Weight of Moisture for Falling Rate Period (Mf(Falling)) and hit the calculate button. Here is how the Falling Rate Drying Time from Initial to Final Weight of Moisture calculation can be explained with given input values -> 30.09932 = ((10-5)/(0.1*2))*(ln((10-5)/(6.5-5))).

FAQ

What is Falling Rate Drying Time from Initial to Final Weight of Moisture?
The Falling Rate Drying Time from Initial to Final Weight of Moisture formula is defined as the time taken for drying in the falling rate period based on drying from initial to final weight of moisture for specified drying conditions and is represented as tf = ((Mi(Falling)-MEq)/(A*Nc))*(ln((Mi(Falling)-MEq)/(Mf(Falling)-MEq))) or Falling Rate Drying Time = ((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Drying Surface Area*Rate of Constant Drying Period))*(ln((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Final Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture))). The Initial Weight of Moisture for Falling Rate Period is the amount of moisture in kg present in the wet solid initially for drying operation, The Equilibrium Weight of Moisture is the amount of moisture in kg present in the solid that is in equilibrium with the solid for the given drying conditions, The Drying Surface Area is the total area in the drying mass transfer operation i.e. exposed in contact with the drying medium, The Rate of Constant Drying Period is the rate of drying that takes place for a given set of drying conditions in the constant rate period & The Final Weight of Moisture for Falling Rate Period is the amount of moisture in kg present in the solid after the completion of drying operation.
How to calculate Falling Rate Drying Time from Initial to Final Weight of Moisture?
The Falling Rate Drying Time from Initial to Final Weight of Moisture formula is defined as the time taken for drying in the falling rate period based on drying from initial to final weight of moisture for specified drying conditions is calculated using Falling Rate Drying Time = ((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Drying Surface Area*Rate of Constant Drying Period))*(ln((Initial Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)/(Final Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture))). To calculate Falling Rate Drying Time from Initial to Final Weight of Moisture, you need Initial Weight of Moisture for Falling Rate Period (Mi(Falling)), Equilibrium Weight of Moisture (MEq), Drying Surface Area (A), Rate of Constant Drying Period (Nc) & Final Weight of Moisture for Falling Rate Period (Mf(Falling)). With our tool, you need to enter the respective value for Initial Weight of Moisture for Falling Rate Period, Equilibrium Weight of Moisture, Drying Surface Area, Rate of Constant Drying Period & Final Weight of Moisture for Falling Rate Period and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Falling Rate Drying Time?
In this formula, Falling Rate Drying Time uses Initial Weight of Moisture for Falling Rate Period, Equilibrium Weight of Moisture, Drying Surface Area, Rate of Constant Drying Period & Final Weight of Moisture for Falling Rate Period. We can use 3 other way(s) to calculate the same, which is/are as follows -
  • Falling Rate Drying Time = (Dry Weight of Solid/Drying Surface Area)*((Initial Moisture Content for Falling Rate Period-Equilibrium Moisture Content)/Rate of Constant Drying Period)*(ln((Initial Moisture Content for Falling Rate Period-Equilibrium Moisture Content)/(Final Moisture Content for Falling Rate Period-Equilibrium Moisture Content)))
  • Falling Rate Drying Time = (Dry Weight of Solid/Drying Surface Area)*((Critical Moisture Content-Equilibrium Moisture Content)/Rate of Constant Drying Period)*(ln((Critical Moisture Content-Equilibrium Moisture Content)/(Final Moisture Content for Falling Rate Period-Equilibrium Moisture Content)))
  • Falling Rate Drying Time = ((Critical Weight of Moisture-Equilibrium Weight of Moisture)/(Drying Surface Area*Rate of Constant Drying Period))*(ln((Critical Weight of Moisture-Equilibrium Weight of Moisture)/(Final Weight of Moisture for Falling Rate Period-Equilibrium Weight of Moisture)))