Early Finish Time Solution

STEP 0: Pre-Calculation Summary
Formula Used
Early Finish Time = Early Start Time+Safety Stock
EFT = EST+S
This formula uses 3 Variables
Variables Used
Early Finish Time - (Measured in Second) - Early Finish Time is the earliest point in time when the scheduled activity can complete.
Early Start Time - (Measured in Second) - Early Start Time is the earliest point in time when the scheduled activity can begin.
Safety Stock - (Measured in Second) - Safety Stock is the extra stock that is always maintained to mitigate any future risks arising due to stock-outs.
STEP 1: Convert Input(s) to Base Unit
Early Start Time: 19 Day --> 1641600 Second (Check conversion ​here)
Safety Stock: 27 Day --> 2332800 Second (Check conversion ​here)
STEP 2: Evaluate Formula
Substituting Input Values in Formula
EFT = EST+S --> 1641600+2332800
Evaluating ... ...
EFT = 3974400
STEP 3: Convert Result to Output's Unit
3974400 Second -->46 Day (Check conversion ​here)
FINAL ANSWER
46 Day <-- Early Finish Time
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Suman Ray Pramanik
Indian Institute of Technology (IIT), Kanpur
Suman Ray Pramanik has created this Calculator and 50+ more calculators!
Verifier Image
Verified by Akshada Kulkarni
National Institute of Information Technology (NIIT), Neemrana
Akshada Kulkarni has verified this Calculator and 900+ more calculators!

Time Estimation Calculators

Expected Waiting Time for Customers in Queue
​ LaTeX ​ Go Expected Waiting Time for Customers in Queue = Mean Arrival Rate/(Mean Service Rate*(Mean Service Rate-Mean Arrival Rate))
Free Float
​ LaTeX ​ Go Free Float = Early Finish Time-Early Start Time-Activity Time
Expected Waiting Time for Customers in System
​ LaTeX ​ Go Expected Waiting Time for Customers in System = 1/(Mean Service Rate-Mean Arrival Rate)
Early Finish Time
​ LaTeX ​ Go Early Finish Time = Early Start Time+Safety Stock

Early Finish Time Formula

​LaTeX ​Go
Early Finish Time = Early Start Time+Safety Stock
EFT = EST+S

What is Early Finish Time?

Early Finish Time is the earliest point in time when the scheduled activity can complete. For its calculation we use the forward pass; we will start from the beginning and proceed to the end. It is equal to the sum of the early start time and the safety stock.

How to Calculate Early Finish Time?

Early Finish Time calculator uses Early Finish Time = Early Start Time+Safety Stock to calculate the Early Finish Time, Early Finish Time is the earliest point in time when the scheduled activity can complete. We use a forward pass for calculating this. Early Finish Time is denoted by EFT symbol.

How to calculate Early Finish Time using this online calculator? To use this online calculator for Early Finish Time, enter Early Start Time (EST) & Safety Stock (S) and hit the calculate button. Here is how the Early Finish Time calculation can be explained with given input values -> 0.000521 = 1641600+2332800.

FAQ

What is Early Finish Time?
Early Finish Time is the earliest point in time when the scheduled activity can complete. We use a forward pass for calculating this and is represented as EFT = EST+S or Early Finish Time = Early Start Time+Safety Stock. Early Start Time is the earliest point in time when the scheduled activity can begin & Safety Stock is the extra stock that is always maintained to mitigate any future risks arising due to stock-outs.
How to calculate Early Finish Time?
Early Finish Time is the earliest point in time when the scheduled activity can complete. We use a forward pass for calculating this is calculated using Early Finish Time = Early Start Time+Safety Stock. To calculate Early Finish Time, you need Early Start Time (EST) & Safety Stock (S). With our tool, you need to enter the respective value for Early Start Time & Safety Stock and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.