Compaction Production by Compaction Equipment when Efficiency Factor is Average Solution

STEP 0: Pre-Calculation Summary
Formula Used
Compaction Production (Effi. Factor is Average) = (16*Width of Roller*Roller Speed*Lift Thickness*Pay Ratio*0.80)/Number of Passes
ya = (16*W*S*L*PR*0.80)/P
This formula uses 6 Variables
Variables Used
Compaction Production (Effi. Factor is Average) - (Measured in Cubic Meter per Second) - Compaction Production (Effi. Factor is Average) gives the effectiveness of soil compaction operations. With "average" efficiency factor indicate that the performance is based on industry standards.
Width of Roller - (Measured in Meter) - Width of Roller is the physical width of the roller used in compaction processes, such as those employed in soil and pavement construction.
Roller Speed - (Measured in Meter per Second) - Roller Speed is the velocity at which a compaction roller moves over soil or other materials during the compaction process.
Lift Thickness - (Measured in Meter) - Lift Thickness is the depth of a compacted layer of fill material placed during construction. This term is important in the compaction process, where fill material is often placed in layers.
Pay Ratio - (Measured in Cubic Meter) - Pay Ratio is the ratio between the effective stress and the total stress in soil mechanics.
Number of Passes - Number of Passes is the number of times a compactor (such as a vibratory roller or a plate compactor) passes over a specific area of soil or aggregate during compaction.
STEP 1: Convert Input(s) to Base Unit
Width of Roller: 2.89 Meter --> 2.89 Meter No Conversion Required
Roller Speed: 3 Kilometer per Hour --> 0.833333333333333 Meter per Second (Check conversion ​here)
Lift Thickness: 7.175 Millimeter --> 0.007175 Meter (Check conversion ​here)
Pay Ratio: 2.99 Cubic Meter --> 2.99 Cubic Meter No Conversion Required
Number of Passes: 5 --> No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
ya = (16*W*S*L*PR*0.80)/P --> (16*2.89*0.833333333333333*0.007175*2.99*0.80)/5
Evaluating ... ...
ya = 0.132266437333333
STEP 3: Convert Result to Output's Unit
0.132266437333333 Cubic Meter per Second -->476.1591744 Cubic Meter per Hour (Check conversion ​here)
FINAL ANSWER
476.1591744 476.1592 Cubic Meter per Hour <-- Compaction Production (Effi. Factor is Average)
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Suraj Kumar
Birsa Institute of Technology (BIT), Sindri
Suraj Kumar has created this Calculator and 2100+ more calculators!
Verifier Image
Verified by Ishita Goyal
Meerut Institute of Engineering and Technology (MIET), Meerut
Ishita Goyal has verified this Calculator and 2600+ more calculators!

Compaction Equipment Calculators

Thickness of Lift given Compaction Production by Compaction Equipment
​ LaTeX ​ Go Lift Thickness = (Production due to Compaction*Number of Passes)/(16*Width of Roller*Roller Speed*Efficiency Factor*Pay Ratio)
Width of Roller given Compaction Production by Compaction Equipment
​ LaTeX ​ Go Width of Roller = (Production due to Compaction*Number of Passes)/(16*Roller Speed*Lift Thickness*Pay Ratio*Efficiency Factor)
Speed of Roller given Compaction Production by Compaction Equipment
​ LaTeX ​ Go Roller Speed = (Production due to Compaction*Number of Passes)/(16*Width of Roller*Lift Thickness*Pay Ratio*Efficiency Factor)
Compaction Production by Compaction Equipment
​ LaTeX ​ Go Production due to Compaction = (16*Width of Roller*Roller Speed*Lift Thickness*Efficiency Factor*Pay Ratio)/Number of Passes

Compaction Production by Compaction Equipment when Efficiency Factor is Average Formula

​LaTeX ​Go
Compaction Production (Effi. Factor is Average) = (16*Width of Roller*Roller Speed*Lift Thickness*Pay Ratio*0.80)/Number of Passes
ya = (16*W*S*L*PR*0.80)/P

What is Compaction?

In geotechnical engineering, soil compaction is the process in which stress is applied to a soil causes densification as air is displaced from the pores between the soil grains.

How to Calculate Compaction Production by Compaction Equipment when Efficiency Factor is Average?

Compaction Production by Compaction Equipment when Efficiency Factor is Average calculator uses Compaction Production (Effi. Factor is Average) = (16*Width of Roller*Roller Speed*Lift Thickness*Pay Ratio*0.80)/Number of Passes to calculate the Compaction Production (Effi. Factor is Average), The Compaction Production by Compaction Equipment when Efficiency Factor is Average formula is defined as the the amount of soil or material that compaction equipment can compact within a specific time frame under average operating conditions. This includes factors such as the machine's capability, soil type, moisture content, and operator efficiency. Compaction Production (Effi. Factor is Average) is denoted by ya symbol.

How to calculate Compaction Production by Compaction Equipment when Efficiency Factor is Average using this online calculator? To use this online calculator for Compaction Production by Compaction Equipment when Efficiency Factor is Average, enter Width of Roller (W), Roller Speed (S), Lift Thickness (L), Pay Ratio (PR) & Number of Passes (P) and hit the calculate button. Here is how the Compaction Production by Compaction Equipment when Efficiency Factor is Average calculation can be explained with given input values -> 1.7E+6 = (16*2.89*0.833333333333333*0.007175*2.99*0.80)/5.

FAQ

What is Compaction Production by Compaction Equipment when Efficiency Factor is Average?
The Compaction Production by Compaction Equipment when Efficiency Factor is Average formula is defined as the the amount of soil or material that compaction equipment can compact within a specific time frame under average operating conditions. This includes factors such as the machine's capability, soil type, moisture content, and operator efficiency and is represented as ya = (16*W*S*L*PR*0.80)/P or Compaction Production (Effi. Factor is Average) = (16*Width of Roller*Roller Speed*Lift Thickness*Pay Ratio*0.80)/Number of Passes. Width of Roller is the physical width of the roller used in compaction processes, such as those employed in soil and pavement construction, Roller Speed is the velocity at which a compaction roller moves over soil or other materials during the compaction process, Lift Thickness is the depth of a compacted layer of fill material placed during construction. This term is important in the compaction process, where fill material is often placed in layers, Pay Ratio is the ratio between the effective stress and the total stress in soil mechanics & Number of Passes is the number of times a compactor (such as a vibratory roller or a plate compactor) passes over a specific area of soil or aggregate during compaction.
How to calculate Compaction Production by Compaction Equipment when Efficiency Factor is Average?
The Compaction Production by Compaction Equipment when Efficiency Factor is Average formula is defined as the the amount of soil or material that compaction equipment can compact within a specific time frame under average operating conditions. This includes factors such as the machine's capability, soil type, moisture content, and operator efficiency is calculated using Compaction Production (Effi. Factor is Average) = (16*Width of Roller*Roller Speed*Lift Thickness*Pay Ratio*0.80)/Number of Passes. To calculate Compaction Production by Compaction Equipment when Efficiency Factor is Average, you need Width of Roller (W), Roller Speed (S), Lift Thickness (L), Pay Ratio (PR) & Number of Passes (P). With our tool, you need to enter the respective value for Width of Roller, Roller Speed, Lift Thickness, Pay Ratio & Number of Passes and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
Let Others Know
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!