Batch Size given Non-productive Time in Turning Solution

STEP 0: Pre-Calculation Summary
Formula Used
Batch Size = (Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/((Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations)))
Nb = (ts+Nt*tst)/((NPT-tln-(tpt*n0)))
This formula uses 8 Variables
Variables Used
Batch Size - Batch Size is the count of similar kinds of products to be manufactured.
Basic Setup Time - (Measured in Second) - Basic Setup Time is the basic time required to load/unload the workpiece and position the tool for production for one component.
Number of Tools Used - The Number of Tools Used is the total number of tools used for manufacturing a batch of products.
Setup Time Per Tool - (Measured in Second) - Setup Time Per Tool is defined as the amount of time taken in setting up the tool while machining.
Non-Productive Time - (Measured in Second) - Non-Productive Time (NPT) refers to the time during which a machine is not actively engaged in producing parts.
Loading And Unloading Time - (Measured in Second) - Loading And Unloading Time is the time required to load/unload the workpiece before the start of machine operation.
Tool Positioning Time Per Operation - (Measured in Second) - Tool Positioning Time Per Operation is defined as the time taken in changing the tool before the start of operation.
Number of Operations - The Number of Operations is defined as the total number of operations done in a batch.
STEP 1: Convert Input(s) to Base Unit
Basic Setup Time: 20.5 Minute --> 1230 Second (Check conversion ​here)
Number of Tools Used: 4 --> No Conversion Required
Setup Time Per Tool: 10 Minute --> 600 Second (Check conversion ​here)
Non-Productive Time: 28.169 Minute --> 1690.14 Second (Check conversion ​here)
Loading And Unloading Time: 30 Second --> 30 Second No Conversion Required
Tool Positioning Time Per Operation: 1.5 Minute --> 90 Second (Check conversion ​here)
Number of Operations: 5 --> No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
Nb = (ts+Nt*tst)/((NPT-tln-(tpt*n0))) --> (1230+4*600)/((1690.14-30-(90*5)))
Evaluating ... ...
Nb = 2.99965293271853
STEP 3: Convert Result to Output's Unit
2.99965293271853 --> No Conversion Required
FINAL ANSWER
2.99965293271853 2.999653 <-- Batch Size
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Parul Keshav
National Institute of Technology (NIT), Srinagar
Parul Keshav has created this Calculator and 300+ more calculators!
Verifier Image
Verified by Rajat Vishwakarma
University Institute of Technology RGPV (UIT - RGPV), Bhopal
Rajat Vishwakarma has verified this Calculator and 400+ more calculators!

Turning Operation Calculators

Diameter of Workpiece given Constant for Cylindrical Turning
​ LaTeX ​ Go Diameter of Workpiece = Constant For Machining Condition*Feed/(pi*Length of Cut)
Turning Length given Constant for Cylindrical Turning
​ LaTeX ​ Go Length of Cut = Constant For Machining Condition*Feed/(pi*Diameter of Workpiece)
Feed given Constant for Cylindrical Turning
​ LaTeX ​ Go Feed = pi*Diameter of Workpiece*Length of Cut/Constant For Machining Condition
Constant for given Cylindrical Turning
​ LaTeX ​ Go Constant For Machining Condition = pi*Diameter of Workpiece*Length of Cut/Feed

Batch Size given Non-productive Time in Turning Formula

​LaTeX ​Go
Batch Size = (Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/((Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations)))
Nb = (ts+Nt*tst)/((NPT-tln-(tpt*n0)))

What is the difference between turning and facing operations?

In the turning operation, the tool generally reduces the diameter of the cylindrical workpiece, which can be done by cutting into the part for some depth and move the tool parallel to the axis of the part. While facing operation reduces the length of the piece, the tool is moved perpendicular to the axis of the part.

How to Calculate Batch Size given Non-productive Time in Turning?

Batch Size given Non-productive Time in Turning calculator uses Batch Size = (Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/((Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))) to calculate the Batch Size, The Batch Size given Non-productive Time in Turning is the count of similar kinds of products to be manufactured. Batch Size is denoted by Nb symbol.

How to calculate Batch Size given Non-productive Time in Turning using this online calculator? To use this online calculator for Batch Size given Non-productive Time in Turning, enter Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Non-Productive Time (NPT), Loading And Unloading Time (tln), Tool Positioning Time Per Operation (tpt) & Number of Operations (n0) and hit the calculate button. Here is how the Batch Size given Non-productive Time in Turning calculation can be explained with given input values -> 2.999653 = (1230+4*600)/((1690.14-30-(90*5))).

FAQ

What is Batch Size given Non-productive Time in Turning?
The Batch Size given Non-productive Time in Turning is the count of similar kinds of products to be manufactured and is represented as Nb = (ts+Nt*tst)/((NPT-tln-(tpt*n0))) or Batch Size = (Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/((Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))). Basic Setup Time is the basic time required to load/unload the workpiece and position the tool for production for one component, The Number of Tools Used is the total number of tools used for manufacturing a batch of products, Setup Time Per Tool is defined as the amount of time taken in setting up the tool while machining, Non-Productive Time (NPT) refers to the time during which a machine is not actively engaged in producing parts, Loading And Unloading Time is the time required to load/unload the workpiece before the start of machine operation, Tool Positioning Time Per Operation is defined as the time taken in changing the tool before the start of operation & The Number of Operations is defined as the total number of operations done in a batch.
How to calculate Batch Size given Non-productive Time in Turning?
The Batch Size given Non-productive Time in Turning is the count of similar kinds of products to be manufactured is calculated using Batch Size = (Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/((Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))). To calculate Batch Size given Non-productive Time in Turning, you need Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Non-Productive Time (NPT), Loading And Unloading Time (tln), Tool Positioning Time Per Operation (tpt) & Number of Operations (n0). With our tool, you need to enter the respective value for Basic Setup Time, Number of Tools Used, Setup Time Per Tool, Non-Productive Time, Loading And Unloading Time, Tool Positioning Time Per Operation & Number of Operations and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.